Stern Hall and Stern Parking Lot
•
On May 22, work began to construct the new road in front of Stern Hall.
This work is expected to be noisy and will include asphalt demolition,
jack hammering, and heavy equipment. This work will stop during dead
and finals weeks, and restart the week of June 19.
Temporary
Stern/Wilbur Lot
•
Construction of the temporary parking lot on the field between Stern
and Wilbur Halls will begin on June 26th. This work will be noisy at
times and will involve the demolition of the basketball courts, removal
of debris and landscaping, and the use of heavy equipment.
• Work to restore the basketball court at the north end of the
field will be concurrent with the installation of the parking lot.
• The above work is expected to take approximately 6 weeks.
Construction
Related Parking Information
•For
current information about parking impacts and replacement parking, please
visit Parking
& Transportation Services construction related impacts web page.
Wilbur
Field Parking Structure (PS 6)
• Work will
continue on this project during dead and finals weeks.
• Excavation work and construction of shoring to support the perimeter
walls of the parking structure will continue throughout the next three
months. Noise and vibrations should be expected due to this work.
Law
School Parking Lot and Student Services Center
April
10 - Late June, the following work
is scheduled to occur in the Law School parking lot:
• During dead and finals weeks, construction activities will continue
in this area. Quiet work will occur between 8:00 AM – 9:00 AM,
and noisy work may begin at 9:00 AM.
• Student Services Access Road and utility work will continue.
A small section of ‘A’ permit parking in the Law School
parking lot will be impacted. This work will be noisy at times, and
there will be increased truck traffic and equipment activity in this
area.
• Construction work will occur directly adjacent to the northwest
and northeast sides of the Student Services Center.
Arguello
Way and Campus Drive Utility Work
• Arguello
Way and Campus Drive Parking and Traffic Advisory
• During dead and finals weeks, construction activities
will continue in this area. Quiet work will occur between 8:00 AM –
9:00 AM, and noisy work may begin at 9:00 AM.
• The underground utility work being conducted from Arguello Way
to Lane A continues. Due to this work, intermittent one way traffic
control will be implemented on Campus Drive between Arguello Way and
the Student Services building. The sidewalk on the north side of Campus
Drive will be closed, and pedestrians should use the sidewalk on the
opposite side of Campus Drive. Signage and traffic flaggers will direct
traffic and pedestrians as necessary.
• The bus stop on the north side of Campus Drive between Arguello
Way and Alvarado Row will remain closed until the completion of all
Campus Drive utility work.. Alternate stops in the westbound direction
are at Campus Drive/Bowdoin Street or Campus Drive/Mayfield Avenue.
• In mid to late June, the second half of the Campus Drive
utility work, from Escondido Road to Lane A, will begin. There will
be additional traffic control, lane restrictions, and the relocation
of bus stops as a result of this work. More information will be available
in the next couple of weeks.
Lane
A
•
Utility work along Lane A will stop during dead and finals, and Lane
A will be re-opened to traffic during this time.
• Work to reconfigure the parking lot behind the Haas Center will
begin on June 19. This parking lot will be closed from June 19 through
approximately August 4.
• Lane A will be re-closed to traffic on June 19, and traffic
to and from the Post Office and Bookstore will be routed along Nathan
Abbott Way.
Historic
House Relocations
•
During dead and finals weeks, work will continue in this area. Quiet
work will occur between 8:00 AM – 9:00 AM, and noisy work may
begin at 9:00 AM.
• Mariposa, Serra and Rogers Houses have been moved to their new
location in front of Bechtel International Center.
• Owen
and Drell house have been moved to their new
location adjacent to Lane A and behind Mars and Sigma Nu Houses.
• April
– September 2006, work will continue on the houses, including
foundation work, seismic upgrades, interior finishes, landscaping and
final parking lot reconfiguration.
• Fall 2006, the houses are scheduled to open..
Thank
you for your patience during construction.
|